Why Projects Fail? Part 4

Project management frameworks in practice: theinfrequency of project-programme communications
C-NOMIS case studymeant that senior management staff were not
This article deals with the fourth of the OGC’saware of the scale of the problems on the C-NOMIS
eight causes of project failure: poor approach toproject.
project and risk management.Summary and solutions
The OGC, in consultation with hundreds of* Ideally, a project management team should remain
experienced management professionals and businessconsistent for the duration of the project. While
experts, has developed best practice guidelines andchanges in staff at lower management levels do not
frameworks for project management and riskusually give rise to a project issue, it is something
management. PRINCE2, the project managementthat should be monitored and, if possible, avoided.
methodology, has become the de-facto standardChanges to corporate/programme staff can also
throughout the UK government, and is the mostusually be absorbed by a solid project management
widely recognised industry qualification in Europe.framework.
M_o_R (Management of Risks) provides a similarlyHowever, changes to senior project management
standardised approach for understanding and handlingstaff (such as the SRO or the project manager) will
the risks to an organisation or a project.require the investment of time and resources, as
Considering the bedrock of project and riskthese roles form the links between the different
management support and advice that the C-NOMISlevels of project activity.
project could fall back on, how did the absence of a* It is not mandatory for senior project management
solid approach to project/risk management becomestaff to have technical experience in the type of
one of the key factors that the NAO identified in theprojects that they manage. Indeed, sometimes
failure of the project?specialists have more difficulties viewing the project
The NAO report highlighted several specific flaws inin terms of products rather than activities, and
the approach to project and risk management usedprovide less adept than the non-specialists.
on the C-NOMIS project:However, the C-NOMIS project was reliant to a large
* Over-reliance on contract staffdegree on the delivery of a complex information
Due to a shortage in skilled personnel, the C-NOMISmanagement system. The project failed, to a
project relied too much on contract staff, which ledsubstantial extent, because it underestimated the
to higher costs, more time spent inducting staff intocost and complexity of the system. An experienced
the project and less staff ‘buy-in’ on theIT project manager, or an experienced project
project.manager equipped with lessons learned on previous
* Inexperienced SRO (Senior Responsible Owner)major IT projects, might have been better positioned
The SRO takes personal responsibility for theto judge and enforce the scope tolerance on the
delivery of the project and any proposed businessproject and deal with IT suppliers.
changes. The first SRO on the C-NOMIS project had* Every project should have external assurance,
little experience of managing large-scale IT projects,particularly a project with such a high profile
and therefore was perhaps ill-equipped to deal with(and such a high budget!) as the C-NOMIS
the scope creep that allowed the budget to soar andproject. Without project assurance it is impossible for
the estimated duration of the project more thanthe corporate/programme management levels to be
double.certain that the project is making adequate progress
* Risks identified but not properly managed– as illustrated by the example of C-NOMIS.
Although it was recognised early on that the* Too few senior managers understand project
C-NOMIS project was high-risk, there was nomanagement and there is reluctance by these people
contingency budget for implementing risk responses.to attend PRINCE2 training by these people. This is a
* Scope creepserious problem that senior managers need to
Poor change management procedures led to theaddress. Project management frameworks such as
incorporation of many adjustments and additions intoPRINCE2 cannot be expected to work if the role
the original product specification. These changesassigned to senior management is not performed
eventually proved too much for the time and budgetproperly. My recommendation would be to send
allocated to the project, and C-NOMIS overran itssenior managers on PRINCE2 courses!
tolerance levels.Looking ahead …
* ‘Good news’ cultureA poor approach to project and risk management
The project manager was the key person reportingundermined the C-NOMIS project. In my next post I
to the programme director, which led to a ‘goodam going to examine the fifth of the OGC causes of
news’ culture and an absence of external qualityproject failure – too little attention paid to
assurance on the project. This, combined with thebreaking down the project into manageable stages.