Project Report Format Example for Project Status

Project reporting is an essential task for any project- Training schedule being delayed by the list of
and the most frequent report is project status. Thedepartment users not being scheduled. Mitigation is to
project status report should include current projectdivert a project team member to accelerate tasks to
status, key risks, project metrics and work done,define list of users to be trained
work in progress and work to be started. It should- Deployment of system to multiple countries is
be targeted at the intended audience and contain thedelayed by expert resources not being available as
level of detail appropriate for that audience.scheduled. Mitigation is to arrange backup people with
Project reporting is an essential task for any projectvendor who will be on call in the event of a resource
and the most frequent report is project status. Theproblem
project manager will normally write the report andProject Metrics
deliver it as a written email update or presentation or- Project schedule is on target with 0 days time
perhaps a combination of both. The information willdelay. 80% of project schedule is now complete
be from the project team and must be current and- Project cost is on target. Total project cost
accurate. Consequently a project manager mustvariance is -5% and 90% of the budget has been
ensure that they are fully in touch with projectspent
status.Work Completed
Purpose of Project Reporting- Acceptance test phases one and two were
The project report format needs to address the keycompleted as scheduled
goals for project reporting:- Test Report has been produced and is in final
- Current, accurate and complete information onapproval
project progress and the project's RAG [Red,- Test environment has now been taken down and
Amber, Green] Status*will be prepared to support the production use of the
- Barriers to successful project delivery and what thenew system
project team is doing to remove those barriers orWork in Progress
prevent them from having an impact- Deployment has started with the installation and
- Understanding of business impact and changeconfiguration of the production environment
- What actions stakeholders need to take, if any- Training material has been finished and is available
* RAG Status is a simple way to indicate the projectfor online and classroom training
status using a traffic light metaphor:- Identification of training needs and scheduling of
- Red = project is either very delayed or significantlytraining has just started
over budget or bothWork to be Started
- Amber = project is delayed or over budget or both- Technical installation report for the production
- Green = project is on track to deliver as scheduledenvironment will start next week as scheduled
and within budget tolerances [i.e. +/- 10%]- Preparation of the production training environment
[The actual definitions should be agreed orwill begin following completion of the production
well-defined beforehand and this RAG status is usefulenvironment
for dashboard style reporting of multiple projects,- Project closure report and release of resources will
especially for senior management.]start next week
Project Report Format Example for Project StatusProject Report Format Example for Project Status
The project status report should include currentThis audience requires the right level information,
project status, key risks, project metrics and workwhich needs to be succinct and focus on the few
done, work in progress and work to be started. Itthings that matter rather than everything that can be
should be targeted at the intended audience andreported. In particular, the audience will want to know
contain the level of detail appropriate for thatif the project is on track and whether it needs any
audience. The frequency, method of update [written,help with any risks or issues.
verbal or both] and who gives the project reportIn the final analysis the presentation, content and
should be defined beforehand. The following is anlevel of detail needs to be determined for the
example the project report format being used.audiences. However, a project will want to
Project Status    "standardise" on a report format to simplify the
Project is on track to successfully deliver as planned.production and delivery of project information and in
Slight delay to sign-off of test report but this will notparticular to not have multiple reports, report formats
impact final delivery. The project will now move toand potentially giving different or confusing
the deployment phase and the relevant experts haveinformation dependent on which report is read.
already started these tasks. Current risks are beingFollowing a single report format and adjusting the
managed and no final risks have emerged to delaylevel of detail for the audience will help to achieve
the Go Live date.consistency and clarity for all concerned.
Key Risks             Copyright 2009. Roger Lever. All Rights Reserved.