| Foreword | | | | requirements which is the main purpose of the |
| I wish to acknowledge the support of Mr John | | | | building and had to be altered at later stage. |
| Tookey University of Auckland for his generously | | | | ï‚§ The Running costs for S.O.H proved |
| support and valuable advises. | | | | expensive , it was a very labour intensive building .In |
| 1. Introduction | | | | 1974 , it operation cost was $A6M, of which only |
| Risk management is one of the most critical project | | | | $A2M was covered by the revenue. Thus costs ruled |
| management practices, to ensure a project be | | | | out small scale opera and the Australian Opera were |
| successfully completed Risk management is thus in | | | | forced to seek a cheaper venue. |
| direct relation to the successful project completion. | | | | 2.5 Construction |
| Project management literature describes a detailed | | | | Engineers who revised the concept noted that the |
| and widely accepted risk management process, which | | | | roof shells were much larger and wider than any |
| constructed from four iterative phases known as risk | | | | shells seen so far. Further, because they stuck up so |
| management plan | | | | height, they would act like sails in strong winds |
| • Risk identification | | | | blowing up the harbour. Thus, the roof would have to |
| • Risk estimation | | | | be carefully designed and constructed to resist such |
| • Risk response | | | | wind pressure. |
| • Planning and execution | | | | The construction was estimated to take about five |
| Risk Identification | | | | years at a cost of A$7 million. Ignoring his request, |
| In this stage , we identify and name the risks , there | | | | the government pressured Utzon into starting |
| are different sorts of risks and we need to decide | | | | construction in 1959, two years ahead of the |
| on a project by project basis what to do with each | | | | architect's proposed schedule. |
| type. | | | | ï‚§ The lack of preparation soon backfired. |
| Risk Quantification | | | | After the completion of the grand podium with an |
| Risk need to be quantified in two dimensions. The | | | | enormous, 86 meter (282ft) wide stair, several years |
| impact of the risk needs to be assessed. The | | | | were spent reworking the design of the roof. |
| probability of the risk occurring needs to be assessed. | | | | • Three tower cranes imported from France |
| For simplicity, rate each on a 1 to 4 scale. The larger | | | | for this job costing $100,000 each and it was the |
| the number, the larger the impact or probability. By | | | | first building constructed in Australia using tower |
| using a matrix, a priority can be established. | | | | cranes. |
| Fig 1 quantification scale matrix (Ref. 11) | | | | • Unfortunately the roof shells were too |
| Risk Response | | | | heavy for the supporting columns that were already |
| There are four things you can do about a risk. The | | | | built, so these were demolished and rebuilt. |
| strategies are: | | | | 2.6 What goes wrong Consequences? |
| • Avoid the risk. Do something to remove it. | | | |  Coast overrun 1300% (Ref. 18) |
| Use another supplier for example. | | | | As feared many experts the project become an |
| • Deflect the risk. Make someone else | | | | engineering financial debacle, lasting 15 years and |
| responsible. Perhaps contracting out or insurance | | | | costing $107 million ($100 million over the initial |
| against (damage , liability, personnel liability etc | | | | estimate). |
| • Mitigate the risk. Take actions to lessen | | | |  Schedule overrun 250% (Ref. 18) |
| the impact or chance of the risk occurring. If the risk | | | | ï‚§ Media and public scandal |
| relates to availability of resources, draw up an | | | | Fig 5 Time /cost Escalation |
| agreement and get sign-off for the resource to be | | | | ï‚§ Management conflict occur between the |
| available. | | | | client and the architect that cause him to resign |
| • Accept the risk. The risk might be so small | | | | before the end of stage III . |
| the effort to do anything is not worthwhile or a | | | | 3. Risk identification quantification |
| contingency plan may be developed to deal with | | | | 3.1 Identification |
| possible effects. | | | | By looking at the project there are some risks |
| Risk Control | | | | appear not used have the most adverse effect on |
| The final step is to continually monitor risks to | | | | the project |
| identify any change in the status, or if they turn into | | | | 1. Poor Cost Estimate. |
| an issue. It is best to hold regular risk reviews to | | | | 2. Incomplete design. |
| identify actions outstanding, risk probability and | | | | 3. Failure to keep within the cost estimate |
| impact, remove risks that have passed, and identify | | | | 4. Failure to achieve the required completion date. |
| new risks. | | | | 5. Changes in project scope and requirements. |
| 1.1 Risk management and construction | | | | 6. Design changes. |
| The construction industry is subjected to more risk | | | | 7. Pressure to deliver project on an accelerated |
| and uncertainty than many other industries. The | | | | schedule. |
| process of taking a project from initial investment | | | | 8. Inaccurate contract time estimate |
| appraisal to completion and into use is complex, | | | | 9. Lack of communication between project |
| generally bespoke, and entails time-consuming design | | | | participants. |
| and production processes. It requires a multitude of | | | | 10. Inadequately defined roles and responsibilities. |
| people with different skills and interests and the | | | | 11. Insufficient skilled staff. |
| co-ordination of a wide range of disparate, yet | | | | 12. Political risks. |
| interrelated, activities. Such complexity is further | | | | 3.2 Qualitative risk analysis |
| compounded by many uncontrollable external factors | | | | Qualitative risk analysis assesses the importance of |
| (Flanagan and Norman, 1983). The construction | | | | the identified risks and develops the prioritized lists |
| industry has a poor reputation in coping with risks, | | | | ,using the 1 to 4 scale matrix discussed above to |
| many projects failing to meet deadlines and cost | | | | quantify identified risks |
| targets. Clients, contractors, the public and others | | | | Risk Probability Impact Risk Importance |
| have suffered as a result (Edwards 1995). This study | | | | 1. Poor Cost Estimate. 3 3 Critical |
| will focus on applying project risk management | | | | 2. Incomplete design. 1 3 High |
| strategies on construction of Sydney opera house | | | | 3. Failure to keep within the cost estimate 3 4 Critical |
| which is a well-known case for cost overrun. | | | | 4. Failure to achieve the required completion date. 4 3 |
| 1.2 The aim of the study | | | | Critical |
| The aim of this study is not to reduce the great | | | | 5. Changes in project scope and requirements. 1 3 |
| achievement of construction such a complicated | | | | High |
| building that changed the face of the city but looking | | | | 6. Design changes. 2 2 Low |
| form management point of view to | | | | 7. Pressure to deliver project on an accelerated |
| ï‚§ Identify and quantify the project risks | | | | schedule. 2 2 Low |
| that been overlooked. | | | | 8. Inaccurate contract time estimate 3 4 Critical |
| ï‚§ Highlight the dangers associated with | | | | 9. Lack of communication between project |
| using poor estimate. | | | | participants. 3 4 Critical |
| 1.3 About the Sydney Opera House | | | | 10. Inadequately defined roles and responsibilities. 1 4 |
| ï‚§ The owner :State government of New | | | | High |
| South Wales | | | | 11. Insufficient skilled staff. 1 2 Low |
| ï‚§ Architect :Jorn Utzon | | | | 12. Political risks. 4 2 Medium |
| ï‚§ Engineer: Ove Arup & Parteners | | | | Three risks were selected for detailed qualitative risk |
| ï‚§ Cost: $102 million | | | | assessment (refer to sheet 1 , 2 and 3) |
| The Sydney Opera House is the busiest performing | | | | Risk Risk Control |
| arts centre in the world. Since its opening in 1973, it | | | | 1. Poor Cost Estimate. Client, Contractor |
| has brought countless hours of entertainment to | | | | 2. Incomplete design. Client , Contractor |
| millions of people and has continued to attract the | | | | 3. Failure to keep within the cost estimate Client |
| best in world class talent year after year. | | | | 4. Failure to achieve the required completion date. |
| 1.4 About the Building | | | | Client, Contractor |
| There are nearly 1000 rooms in the Opera House | | | | 5. Changes in project scope and requirements. |
| including the five main auditoria. There is also a | | | | Engineers |
| Reception Hall, five rehearsal studios, four | | | | 6. Design changes. Contractor |
| restaurants, six theatre bars, extensive foyer and | | | | 7. Pressure to deliver project on an accelerated |
| lounge areas, sixty dressing rooms and suites, library, | | | | schedule. Engineers |
| an artists' lounge and canteen known as the "Green | | | | 8. Inaccurate contract time estimate Contractor, |
| Room", administrative offices and extensive plant and | | | | Client |
| machinery areas. The building covers about 1.8 | | | | 9. Lack of communication between project |
| hectares (4.5 acres) of its 2.2 hectare (5.5 acre) site. | | | | participants. Engineers, Contractor, Client |
| It has about 4.5 hectares (11 acres) of usable floor | | | | 10. Inadequately defined roles and responsibilities. |
| space. It is approximately 185 m (611 ft) long and | | | | Engineers, Client |
| 120m (380 ft) wide at its widest point. The highest | | | | 11. Insufficient skilled staff. Client |
| roof vault (above the Concert Hall) is 67m (221 ft) | | | | 12. Political risks. Contractor |
| above sea level. | | | | 3.2 Risk response |
| The roofs are made up of 2,194 pre-cast concrete | | | | 3.2.1 Risk Avoidance |
| sections. These sections weigh up to 15.5 tones (15 | | | | As discussed most of the risk could be avoided by |
| tons) each. They are held together by 350 km (217 | | | | only |
| miles) of tensioned steel cable. The roofs weigh | | | | • Completed design . |
| 27,230 tones and are covered with exactly 1,056,056 | | | | • Estimating at a very detailed level. |
| Swedish ceramic tiles arranged in 4,253 pre-cast lids. | | | | • Not selecting untested design . |
| The entire building weighs 161,000 tones. It is | | | | • Using local Architecture office will reduce |
| supported on 580 concrete piers sunk up to 25 m | | | | many and more communication and experienced |
| (82 ft) below sea level. The roofs are supported on | | | | architecture designer |
| 32 concrete columns up to 2.5 m (8 ft) square. The | | | | 3.2.2 Risk transfer |
| exterior and interior walls, stairs and floors are faced | | | | • Using a fixed price contract will transfer |
| with pink aggregate granite which was quarried at | | | | construction risk to the contactor. |
| Tarana in New South Wales. The two woods used | | | | • Obtaining Insurance to cover costly risks. |
| extensively to decorate the interiors are brush box | | | | 3.2.3 Mitigate the risk |
| and white birch plywood which were both cut in | | | | Risk analysis shows that no clear management |
| northern NSW. There are 6,225 sq m (67,000 sq ft) | | | | process for controlling the project however using an |
| of glass, made in France, in the mouths of the roofs | | | | experienced project manager would effectively |
| and other areas of the building. It is in two layers - | | | | reduce probability or impact of risks to an acceptable |
| one plain and the other demi-topaz tinted. About | | | | level. |
| 2,000 panes in 700 sizes were installed. | | | | 4. Assessment forms |
| There are 645 km (400 miles) of electrical cable. 120 | | | | Following a three assessment forms for 3 of the |
| distribution boards regulate the power supply, | | | | significant risks |
| equivalent to the needs of a town of 25,000 people. | | | | Performa for a Qualitative Risk Assessment (sheet 1) |
| Twenty-six air-conditioning plant rooms move more | | | | Reference No: 6 Date:25/06/2007 |
| than 28,500 cubic meters (1,000,000 cubic feet) of | | | | Potential risk: Importance of Risk: Low |
| air per minute through 19.5 km (12 miles) of ducting. | | | | Design changes |
| Fig 2 Sydney opera house (Ref. 6) | | | | Probability Medium |
| Fig 3 Sydney opera house during construction (Ref. | | | | Consequence Medium |
| 7) | | | | Stage of the project affected by this risk: |
| Fig 4 Sydney opera house shells (Ref. 7) | | | | Construction stage |
| Fig 4 Sydney opera house shells (Ref. 7) | | | | Statement of risk: |
| 1.5 Design Stage | | | | Cost and schedule overrun |
| The original concept for the project was a sketch | | | | (The factor that could cause it to occur) |
| submitted by Danish architect , Jorn Utzon .Judges | | | | Political business interest |
| selected it from an international open competition | | | | Site problems |
| that ended with 233 entries from 11 countries. | | | | (any relationship or dependency on other risks) |
| Thought happy to win the competition Utzon was | | | | Incomplete design |
| mildly shocked .although his concept had caught the | | | | (the likelihood of occurring) |
| attention of the judges, it consisted only if simple | | | | Medium |
| sketches with no plans or even perspective drawings | | | | (how it could be affected) |
| , because the design was so unique , some people | | | | Design checking prior leaving the design office |
| presumed it would also be inexpensive to build. No | | | | Project: |
| one knew how it would be build , and some experts | | | | Sydney opera house |
| questioned that it could be built at all. | | | | Client: |
| In spite all uncertainty , the initial project cost | | | | New South Wales government Risk Analyzed by: |
| estimate was pit at $7million.The government would | | | | Khaled |
| use profits from a series of state run lotteries to pay | | | | Performa for a Qualitative Risk Assessment (sheet 2) |
| the project. | | | | Reference No:1 Date: 25/06/2007 |
| The government was worried that the people | | | | Potential risk: Importance of Risk: Critical |
| scrutinizing the design might raise question about the | | | | Poor Cost Estimate |
| potential problems hat would stall the project they | | | | Probability High |
| thus quickly mover ahead and divided the work into | | | | Consequence High |
| three main contracts :the foundation and the building | | | | Stage of the project affected by this risk: |
| except the roof, the roof, and the interior and | | | | Design stage |
| equipment. | | | | Construction stage |
| 1.6 Construction stage | | | | Statement of risk:major source of complainttime |
| Many of the world's best-known construction | | | | consuming |
| companies were involved in building | | | | (the factor that could cause it to occur) |
| Sydney Opera House including Arups Structural | | | | Changes in project scope and requirements |
| Engineering, Hornibrook and Rider Hunt, the | | | | (any relationship or dependency on other risks) |
| construction work of S.O.H was divided into three | | | | Inadequately defined roles and responsibilities. |
| distinct stages as follows (Ref. 19) | | | | (the likelihood of occurring) |
| • Stage I | | | | Height |
| Sub structure , concrete structure from the | | | | (how it could be affected) |
| foundation up to the auditoria seating levels excluding | | | | Effective project management |
| any finishes. | | | | Clearly defined roles |
| • Stage II | | | | Project: |
| Superstructure or shells , concrete roof vaults or | | | | Sydney opera house |
| major and minor halls an restaurants , including the | | | | Client: |
| claddings. | | | | New South Wales government Risk Analyzed by: |
| • Stage III | | | | Khaled |
| Everything not included in stages I and II , stage | | | | Performa for a Qualitative Risk Assessment (sheet 3) |
| towers, all interior finishes, exterior paving and | | | | Reference No:9 Date: 25/06/2007 |
| cladding, glass walls , all electrical and mechanical | | | | Potential risk: Importance of Risk: Critical |
| services. | | | | Lack of communication between project participants. |
| After he was elected premier of New South Wales in | | | | Probability high |
| 1965, Askin attempted to force Utzon reduce costs | | | | Consequence high |
| by withholding payments. In 1966 Utzon resigned and | | | | Stage of the project affected by this risk: |
| returned to his native Denmark. He never even | | | | Construction stage |
| returned to see his masterpiece completed. | | | | Design stage |
| The construction of the Sydney Opera House was | | | | Statement of risk: |
| now handed over to a group or Australian architects. | | | | Insufficient working drawing details |
| Fortunately, the exterior had already been completed | | | | Late and in adequate information |
| by then so that the impact of the altered design on | | | | Major costly errors. |
| the overall structure was minimal. The project was | | | | (the factor that could cause it to occur) |
| finally completed in 1973 after a construction period | | | | Lack of management |
| of 14 years and an expenditure of over $A100 million, | | | | Interest conflict between project participation |
| almost 15 times the estimated budget. | | | | (any relationship or dependency on other risks) |
| 2. Risk management strategies at S.O.H | | | | Incomplete design |
| 2.1 Financial | | | | (the likelihood of occurring) |
| Despite of all cost escalation , taxpayer had little to | | | | Height |
| pay .Virtually all the costs were covered by the | | | | (how it could be affected) |
| proceeds of State Lotteries. The continued need to | | | | Proper project management |
| the subside the running costs of the opera house | | | | Project: |
| were financed by the continuation of the Lottery | | | | Sydney opera house |
| State. The first estimate for the Sydney Opera | | | | Client: |
| House was $7.2 million in Australian dollars. Once | | | | New South Wales government Risk Analyzed by: |
| started, however, costs kept rising and just to | | | | Khaled |
| complete the building cost $102 million. | | | | 5. Lessons learned |
| 2.2 Political | | | | • Risk must be identified to be managed |
| Political risks are often occur in government project | | | | • A poorly defined risk structure will breed |
| as they often hide information affecting the | | | | more risks. |
| community's support, which in turn affect the | | | | • A proper risk management strategy would |
| effectiveness of the feasibility study . S.O.H we | | | | planning. |
| mostly severely effect by political decisions | | | | • All designs and calculations should be |
| 2.2.1 Media and public deception | | | | checked before they leave the design office further |
| In S.O.H. the original budget of seven million Australian | | | | check calculation should be made by the authority , |
| dollars was not a real but a political budget .The | | | | many errors that escape are picked up and corrected |
| labour government of New South Wales the main | | | | during construction .This often cause a delay to the |
| proponent of the S.O.H, wanted the project started | | | | project and might effect the cost. |
| before elections in March 1959-this would reduce the | | | | • The goal is to prevent political and |
| risk of the stopping the project in case Labour lost | | | | business interests from interfering with design and |
| the elections (8). | | | | thus to arrive at an outcome as close as possible to |
| 2.2.2 Deceptive cost estimate | | | | the original design drawings. |
| Kim Utzon explains in lieu of his father "It was a | | | | • Continually monitor risks to identify any |
| political decision to publicize a low budget for the | | | | change in the status, or if they turn into an issue. It |
| building, which was expected to gain approval in the | | | | is best to hold regular risk reviews to identify actions |
| political system, but which very quickly was | | | | outstanding, risk probability and impact, remove risks |
| exceeded. So even if the cost overrun turned to be | | | | that have passed, and identify new risks. |
| 1400% in relation to the publicized budget, this | | | | • Risk management is not one off activity |
| budget was an eight of the real budget of the | | | | instead, it should be applied continuously through the |
| building .So the real overrun is only 100% the rest | | | | project life. |
| was politics". | | | | • The best way to control budget is not to |
| 2.2.3 Political construction date | | | | proceed with the building unlit you have all the |
| The start of construction for stage I was fixed ., | | | | drawings complete. |
| largely for political reasons , as the 2nd March | | | | 6. Conclusion |
| 1959.Thus Proceeding with construction before | | | | Study clearly identify the great importance of risk |
| completing the design process which is a great risk . | | | | management on construction projects, negligence will |
| 2.2.4 Political design changes | | | | lead to an expensive cost effecting the project |
| On 1966 major hall was changed from dual purpose | | | | successes. |
| for concert and opera to a single purpose concert | | | | A risk analysis project shows a large number |
| hall, the dual purpose was a requirement of the | | | | qualitatively ranked as 1 , those risks have a high |
| competition . | | | | probability of occurrence and height consequence |
| 2.3 Structural | | | | shared between the client 42% , the contractor |
| 2.3.1 The Supporting points | | | | 36% and the engineer 21% . |
| Arup and his engineers knew very well that the | | | | This indicates that it was a very risky project |
| cross-section shape Utzon chose was far from ideal | | | | nevertheless risks were either downplayed or ignored |
| known structures, however they could not suggest | | | | , and not much was done to keep them under |
| changing to the shape as it will alter the appearance | | | | control, the project management strategies was only |
| of the roof drastically. | | | | focused on keeping the project going no matter how |
| 2.3.2 The roof | | | | it is going . |
| A question should be asked if this design is | | | | Finally although the opera house put Sydney on the |
| achievable?. The competition judges choose a | | | | world map, both architecturally and culturally but from |
| complex art design without asking how it will be | | | | project management perspective it was a |
| deigned? later on it was a major cause for delaying | | | | spectacular failure as a consequence of ignoring risk |
| the roof design if this point was been considered | | | | management. |
| they should either choose a simple shape or a known | | | | References |
| geometry, at this stage computer program analysis | | | | 1. [Accessed 2 May 2007]. |
| was not yet been introduced that means only manual | | | | 2. [Accessed 2 May 2007]. |
| process can be used to calculate the forces acting on | | | | 3. Edwards, L. (1995). Practical risk management in the |
| the structure. | | | | construction industry, Thomas Telford, London |
| 2.3.3 Lack of suitable boundary condition. | | | | 4. Flyvbjerg, Bent, "Design by Deception: The Politics |
| Another technical problem that the engineer had to | | | | of Megaproject Approval", Harvard Design Magazine, |
| solve was the lack of boundary condition that leads | | | | Volume 22, 2005. |
| to some earthwork as sub base for the structure | | | | 5. [Accessed 2 May 2007]. |
| foundation. | | | | 6. [Accessed 2 May 2007]. |
| 2.4 Technical | | | | 7. [Accessed 2 May 2007]. |
| Utzon, ware of possible technical problems since his | | | | 8. Murray ,21-22. |
| design required advanced technology not yet | | | | 9. Murray, P: The Saga of the Sydney Opera House, |
| available, requested additional time to tackle those | | | | 2004, Spon Press (UK), ISBN 0415325218 |
| challenges Utzon faced the task of converting the | | | | 10. [Accessed 25 Jun 2007]. |
| concept into a design form which a structure could | | | | 11. Neville Turbit |
| be built, but he had no prior experience in the design | | | | 12. John Tookey civil 703 lecture notes University of |
| and construction of such a large building. Because of | | | | Auckland. |
| this lack of plans, detailed design drawings, and | | | | 13. Office of Project Management Process |
| estimates of materials, little existed from which cost | | | | Improvement "Project Risk Management Handbook" |
| could be determined. | | | | 14. Peter Murray "The dramatic storey of the design |
| 2.4.1 Design errors and omissions | | | | and construction of the icon of modern |
| • Unfortunately, the roof shells were too | | | | Australia"(London and New York: Spon |
| heavy for the supporting columns that were already | | | | Press,2004),105. |
| built, so these were demolished and rebuilt. These | | | | 15. Roger Flangan & George Norman "Risk |
| and several other setbacks led to delays and | | | | Management and Construction". Blackwell Scientific |
| increasing cost overruns. | | | | Publications ISBN 0-632-02816-5. |
| • The original design called for two theatres. | | | | 16. [Accessed 2 May 2007]. |
| The government changed its mind and required the | | | | 17. [Accessed 2 May 2007]. |
| building to be altered and that four theatres now be | | | | 18. Woodward, Hugh PMP, PowerPoint Presentation |
| incorporated into the design | | | | to NASA on March 23, 2005, |
| • The foundation been demolished to suit | | | | 19. Yozo Mikami "Utzon's Sphere" page 46 |
| the new roof design loads. | | | | Shokikusuha Tokyo ISBN 4-395-00712-0 |
| 2.4.2 Fitness for purpose. | | | | 20. Ziegler, Oswald L. (ed) Sydney Builds an Opera |
| ï‚§ The main design overlooked acoustic | | | | House. |