Increasing Project Value through Risk Management

Most organizations have more project proposals and$5,000 + $2,000 + $8,000 or $15,000. The return is
ideas than they can realistically fund. This meansnow $20,000 - $15,000 or $5,000, making the project
project teams are competing for project approvalsubstantially less attractive than it originally appeared.
and funding. Consequently, project champions oftenBut by managing the risks, the value of this project
conceal or exaggerate the true value of theircan be increased to a level that again makes it
projects. Teams and organizations typically focus onattractive.1. First, the requirements could be tightened
the up-front costs of a project and the expectedby first developing a proof-of-concept or simply
return. Other costs are glossed over or ignoredby delaying the project until the uncertainties can be
entirely, and risk assessment is treated as aeliminated. By taking this approach, the
perfunctory afterthought. This focus on the up-frontvalue of the project can be increased by eliminating
costs and the net return is only half of the story,the $5,000 reduction for the risk of uncertainty.2. A
however.It may be time to stop thinking of riskproof-of-concept could also be evaluated by the
assessment as the killjoy exercise which drains thesales force to ensure that they will not
enthusiasm from your project and to start thinkingneed training, as feared, thereby eliminating the
of it as a tool for enhancing your project'ssecond risk and increasing the project's
value.Understanding the Fundamentals:A project risk isvalue by an additional $2,000.3. Finally, although
any problem that could cause some loss or threatenexternal uncertainties cannot be eliminated, mitigation
the success of the project1. Risks differ from issuesand contingency
because they refer to the future or to the potentialplans can be put in place to reduce the overall
for adverse outcome."A risk consists of a conditionimpact on the project's value. For example,
which is not currently true, the likelihood that theinstead of structuring the project as an all-or-nothing
condition will materialize, and a consequence or impactproposition, perhaps it can be
on the project if the condition does materialize."Riskimplemented so that parts or stages of it can be
management is the process of identifying, analyzing,adapted to many different environments.
and addressing project risks proactively to maximizePerhaps the data structures and encoding can be
positive consequences (opportunities) and minimizeseparated from the database implementation
negative consequences (losses). Risks are addressedso that if organizational changes arise that undermine
by formulating mitigation plans, which are aimed atthe implementation, the data structures can
reducing the likelihood that the condition willstill be used in the implementation ultimately adopted
materialize, and contingency plans, which are aimed atby the organization. If a third of the work can
addressing the condition when it does materialize.Asbe salvaged, the value of the project is increased by
mentioned above, the value of a project is$2,640 ($8,000 x .33).This brings the total increase in
determined by its net return and its risks. The netreturn as a result of risk management to
return on the project is equal to the present value of$9,640.After risk management, the value of the
the project minus the costs (return = present value -project is $14,640 ($5,000 return after risk
costs). This return assumes that the project willassessment
proceed as planned and budgeted - that is, it+ total increase in return after risk
assumes a risk-free project. But projects are rarelymanagement).Conclusion:The true value of a project
risk-free. To get a true assessment of the project,cannot be evaluated without being realistic about the
the return must be evaluated against thecosts of the undertaking, including the risks. Risks
risks.Applying Risk Management:Suppose I have athat are simply acknowledged and built into the costs
project proposal to unify two corporate databases. Iwill always lessen the value of a project, motivating
estimate that this will save the organization $100,000project managers to report overly optimistic
over five years and that it will cost $80,000 tooutlooks, which undermines the very reason for
implement. The return is $20,000 without factoring inconsidering risks. But if risks are actively managed by
any risks, but there are risks.1. Due to somemeeting them head-on, formulating mitigation and
uncertainty in the requirements, there is a 50%contingency plans and treating risk management as
likelihood that the development effort will cost anan ongoing process, risks can be minimized. As a
additional $10,000. This comes to a reduction of theresult, project values can be increased, and
return by $5,000 ($10,000 x .50).2. Although theorganizations will get a more accurate and consistent
project team has assurance from sales that theunderstanding of project values.About Ralph
impact upon the sales force will not be substantial,Dandrea:Ralph Dandrea is the President of ITX Corp.,
the team believes that there is still a 25% likelihoodand leads its Business Performance practice. He is
that upon seeing the changes, sales will requireexperienced in business and information technology
additional training, costing $8,000, thereby reducingmanagement and holds graduate degrees in business
the return by $2,000 ($8,000 x 25).3. Due to someand law. ITX(R):ITX Corp is a business consulting and
inherent uncertainties regarding the technologies, astechnology solutions firm focused in eight practice
well as the direction of the organization and someareas including Business Performance, Internet
anticipated acquisitions, there is a 10% likelihood thatMarketing, IT Staffing, IT Solution Strategies, IT
the entire project will fail or be superseded by otherSolutions Implementation, Technical Services, Internet
efforts. This means a reduction of the return byServices, and Technology Research.To learn more
$8,000 ($80,000 in overall project costs x .10).Whenabout what ITX can do for you visit our website at
all risks are factored, the reduction on the return isor contact us at (800) 600-7785.